Q: When is SEPA environmental review required?

A:

Environmental review is required for any proposal which involves a government "action," as defined in the SEPA Rules (WAC 197-11-704), and is not categorically exempt (WAC 197-11-800 through 890). Project actions involve an agency decision on a specific project, such as a construction project. Nonproject actions involve decisions on policies, plans, or programs, such as the adoption of a comprehensive plan or development regulations, or a transportation plan.

Q: Who is responsible for doing SEPA environmental review?

A:One agency is identified as the "lead agency" under the SEPA Rules WAC 197-11-924 to 938, and is responsible for conducting the environmental review for a proposal and documenting that review in the appropriate SEPA documents (DNS, DS/EIS, adoption, addendum). Two or more agencies may share lead agency status by agreement, but a single environmental analysis would be conducted and all SEPA documentation is issued jointly.

Q: How can a permit applicant start the SEPA process?

A: The environmental review process is conducted by the designated lead agency –which is usually the local permitting agency for private projects. Often the SEPA review starts when the applicant completes and submits an Environmental Checklist with the required permit application.

Q: How long does a SEPA review last?

A: The environmental information in a specific SEPA review is used to inform upcoming agency decisions but if those decisions are delayed then there is no set expiration of the SEPA documents. However, there are often changes in the proposal, existing environment or scope of impacts that require additional studies and new SEPA notice and comment opportunities.

Q: What types of proposals are categorically exempt?

A:Certain types of proposals are automatically exempt from the threshold determination and EIS preparation because they are a size or type unlikely to cause a significant adverse environmental impact. Examples include minor new construction of residential, commercial or storage structures and minor road and street improvements. Other exemptions include maintenance activities, enforcement and inspection activities, issuing business licenses, storm/water/sewer lines eight inches or less, etc.

Q: When do categorical exemptions not apply?

A:Some exemptions contain exceptions in which the exemption does not apply.These include proposals involving lands covered by water; projects requiring a license to discharge to the air or water; or projects requiring a rezone. A city or county may also eliminate some exemptions if the project is located within a designated critical area.

Q. If a proposed construction project is exempt from SEPA but the clearing and grading associated with the construction exceeds the maximum of the threshold in the “landfill and excavation” exception, isSEPA required?

A: The list of SEPA exemptions for “minor new construction”cover the “activity” of constructing a residence, office, shed, parking lot, a landfill or excavation type of proposal. Ecology views the list as mutually exclusive, in part due to the preface to the list: A proposal to build or locate a house is considered a “residential” type of “construction in question.”

Q. What is the definition of “recognized historical significance” as used in the exception to minor new construction exemptions?

A. A property that is eligible for official listing on a local, state or national historic register can be considered “significant” for the purpose of this exception.Applicants and lead agencies should consult the Department of Archaeological and Historic Preservation (DAHP) prior to making an assumption about the applicability of this exemption.

Q. If a project spans two or more jurisdictions with different exemption thresholds, which exemption levels apply?

A. If a proposal lies within two jurisdictions, the lower level threshold controls the total proposal, regardlesswhich agency is lead. For example, the major portion of a proposed 16-unit residential development lies within the city limits of Bigcity, which has raised the residential threshold to 20 units. A small portion of the development, however, lies within the city-limits of Quiettown, which has not raised itsresidential threshold. Alhough Bigcity is lead agencyand all 16 units will be constructed within Bigcity jurisdiction, Quiettown’s lowerthreshold must be applied to the entire proposal and the project would not be exempt.

Q. Is “mixed use” defined?

A. “Mixed use” is not defined in SEPA. For purposes of developing, the term should be defined as a mix of residential and commercial/retail development. A city or county comprehensive plan should define the type and level of developmentallowed in the mixed use category.

Q. Under the infill exemption, are infrastructure improvements needed for an exempt residential or mixed use development also exempt?

A.

No. If infrastructure improvements are needed, such as a sewer or water distribution line extension, the improvement will not be exempt from SEPA review unless it meets the exemption level specified in SEPA rules.

Q: What is the difference between lead agency and an agency with jurisdiction?

A:The lead agency is responsible for all procedural aspects of SEPA compliance. An agency with jurisdiction under SEPA has an “action” or decision regardingsome aspect of the total proposal. All agencies with jurisdiction have a legal responsibility to consider the environmental information disclosed in the SEPA process.

Q: Can a special district, such as a school district or port district, be SEPA lead agency?

A:SEPA rules define a local agency as "any political subdivision, regional governmental unit, district, municipal or public corporation." If an agency is proposing a project or nonproject action, they arelead agency under SEPA. This meansa school district would be lead agency for school construction, a port would be lead agency for a port comprehensive plan, while the WashingtonState Parks and Recreation Commission would be lead agency for developing or remodelinga state park.

Q: Which agency is SEPA leadwhen an agency is proposing a projectlocated within the jurisdiction of another agency?

A:SEPA rules are clear: Theagency proposing a project is the default lead SEPA agency. However, leadagency status may be transferred if all agencies with a jurisdiction agree.

Q: Can two or more agencies share lead agency status?

A:Yes, any number of agencies can agree to share lead agency status, with one agency designated as "nominal lead agency." The agencies should develop an agreementdefining the duties and responsibilities of each agency, how to deal with differing opinions, etc.

Q: What is the "threshold determination" process?

A:The threshold determination process isused to evaluate the environmental consequences of a proposal and determine whether itis likely to have any "significant adverse environmental impact." This determination is made by the lead agency. It is documented in either a Determination of Nonsignificance (DNS) or a Determination of Significance (DS) and the subsequent preparation of an EIS.

Q: What is a "significant" adverse environmental impact?

A:State SEPA rulesdefines "significant" as "a reasonable likelihood of more than a moderate adverse impact on environmental quality." The term “reasonable likelihood” means it is not remote or speculative. The phrase “more than moderate” is based on intensity and severity; intensity depends on the magnitude and duration of an impact while severityis weighed along with the likelihood of its occurrence. An impact may be significant if its chance of occurrence is not great, but the resulting environmental impact would be severe.

Q: What is a "Determination of Nonsignificance?"

A:A"Determination of Nonsignificance," or DNS, documents the responsible official’s decisionthat a proposal is unlikely to have significant adverse environmental impacts.

Q: Does a DNS always have a public comment period?

A:No.Therefive criteria to determine whether a comment period is required:

  1. Another agency with jurisdiction
  2. Non-exempt demolition activities
  3. Non-exempt grade and fill permits
  4. A mitigated DNS or anyDNS issued after a determination of significance has been is withdrawn
  5. An action under the state Growth Management Act.

If a comment period is required, the lead agency must give public notice and circulate the DNS and checklist. If a comment period is not required, no public notice or distribution is required.

​Q: What is the difference between a Determination of Nonsignificanceand a mitigated Determination of Nonsigficance?

A:A mitigated Determination of Nonsignificance (DNS) has had more public process and greater scrutiny because the proposal has likelysignificant adverse impacts. The lead agency issues a mitigated DNS in lieu of preparing an EIS when there is assurance that specific enforceable mitigation will successfully reduceimpacts to a nonsignificant level.

Q: What is the "optional DNS" process?

A:The optional DNS process allows alead agencyto combine the SEPA comment periodwith the notice of application (NOA) prior toactually issuing the DNS. The notice of applicationmust statethe optional DNS process is being used andthe public'sopportunity to comment will be limited. It also means all mitigation conditions under consideration alsomust be identified. After the end of thecomment period, the lead agency may issue the DNS without a second comment period.

Q: When is an environmental impact statement required?

A:An EIS is required for any proposal likely to have a significant adverse environmental impact in which actions to offset or mitigate the impactswould reduce them to a nonsignificant level. The applicant and lead agency may work together to revise the proposal’s impacts or identify mitigation measures that would allow the lead agency to issue a determination of nonsignificance.

Q: What is "scoping"

A:If the lead agency issues a determination of significance, the first process stepisdetermining the "scope" of the EIS — or those issues and alternativesneeding to be evaluated. The scoping process allows the public and other agencies to comment on the EIS scopeand assist the lead agency in identifying issues and concerns. The lead agency can use a standard scoping notice with a written comment period, or they can use expanded scoping that might include public meetings, surveys, and other methods to involve the public in the process.

Q: What documentation is needed after thecomment period forscoping is done?

A:After the public comment period closes, the project proponent can request that the lead agency make a determination regardingthe scope of the EIS.While no other documentation is required under SEPA,agencies may choose to issue a public scoping document, respond to public comments, or announce whichalternatives will be addressed in the EIS.

Q: Does the final EIS include allthe information in the draft EIS?

A:Yes, in most cases. The draft EIS is exactly that — a draft. The final EIS can be significantly different from the draft because the lead agency revises the EIS based on comments and new information. The final EIS also includes all comments received on the draft EIS as well asthe lead agency’s responses. If no substantive comments are received, the lead agency may choose toissue a new fact sheet, including a possible addendum, to be attached to the draft document.

Q: Does the EIS need to include the addresses of commenters, agencies, and citizens on the distribution list?

A:SEPA rules require that a "distribution list" be included that lists all commenters' names but there's nothing about needing theiraddresses.

Q: Can an agency prepare an addendum to a DNS? If so, what is the format? Are public notice and distribution required?

A:If an agency intends to revise a DNS before completing the SEPA process, it is best if the lead agency issues a“Modified” or “Revised” DNS.An addendum may be added to the existing Environmental Checklist or a revised checklist may be used to detail new information.Unless the threshold determination involves a mitigated DNS,a new public notice and comment process is not usually required.However, we strongly advise the lead agency opena new comment perioddueto higher scrutiny involving significant impacts and loss of the EIS process.

Q: If a project has been reviewed under SEPA but new information indicates supplemental review is needed for a portion of the project, can construction of the unaffected portionproceed?

A:SEPA rules stateno action that would foreclose options canbe taken until the environmental reviewhas been completed.

Q: What is SEPA substantive authority?

A:SEPA substantive authority is the regulatory authority granted to all state and local agencies to condition or deny a proposal to ensure identifiedenvironmental impacts can be sufficiently offset.To use SEPA substantive authority, an agency must have adoptedSEPA policies.

Q: Are the mitigation measures identified in the SEPA document (DNS or EIS) mandatory?

A:Not necessarily. Mitigation conditions required underSEPA substantive authority must be included as conditions on a permit, license, or approval, before they become mandatory or enforceable. Mandatory mitigation required under other local, state, or federal laws may also be included on the DNS by the lead agency for the information of reviewers.

Q: How much review is required at the planning stage for project impacts?

A:Lead agencies are responsible for considering the probable significant adverse impacts of planning actions such as adoptingcomprehensive plans and development regulations. If the proposed plans or regulationswould allow activities to occur that are likely to have significant adverse impacts, those impacts must be addressed in the environmental review of the planning action. The more detailed the review at the planning phase, less review will be needed at the project stage.

Q: Doesa nonproject EIS need to follow a specific format?

A:The only requirements are that the document begin with a fact sheet and contain an environmental summary. An agency may choose whatever format they feel would best present the alternatives and environmental analysis. Separate sections on affected environment, significant impacts, and mitigation measures are not required in integrated documents as long as this information is summarized and supported in the record. The rules for integrated documents stress that the format should be dictated by attention to the quality, scope, and level of detail of the information and analysis.

Q: What is an "alternative" when preparing an EIS for a comprehensive plan? How is the no action alternative defined?

A:A range of alternatives should be evaluated that explore the different land use options including different urban growth area boundaries, characteristics and densities of development, etc. The no-action alternative for a comprehensive plan is generally defined as no change in existing regulation — such zoning, development regulations, critical area ordinances, etc. The environmental impacts of predicted growth under this "no-action" scenario is then compared toother alternatives.

Q: When integrated with a comprehensive plan, what is the timing of a final EIS?

A:When the integrated document contains the final EIS and the plan,the final EIS andGMA document may be adopted occur together without needing aseven-day waiting period.

Q: Is additional environmental review required when the final action is different from the alternatives analyzed in an EIS?

A:If the final approved proposal falls within the range of alternatives analyzed in the EIS and all likely significant adverse impacts have been evaluated, additional review would not be required. For example, if one of the EIS alternatives evaluates the impacts of four urban centers and another alternative evaluates the impacts of six urban centers, and the lead agency selects five urban centers as the preferred alternative, it is possible the impacts would have been covered by the range of EIS alternatives.

Q: Are there opportunities to appeal SEPA documents or the use of SEPA substantive authority?

A:The lead agency has the option of allowing an administrative appeal and may allow an appeal of either procedural issues, substantive decisions, or both. If the administrative appeal process has been exhausted or is unavailable, a judicial appeal can be filed in a timely manner.

Q: What is an "underlying governmental action"?

A:The underlying governmental actionis the action that must be taken by an agency to authorize a proposal. Actions include issuing a permit or license, approvingfunding,or adoptinga plan, ordinance,rule, or other actions.

Q: Can an applicant appeal an agency's decision to require mitigation measures?

A:Yes, if the agency does not offer an administrative appeal on the substantive use of SEPA, the applicant may file a judicial appeal of the mitigation with a challenge to the underlying action.

Q: What is the appeal process when a state agency is SEPA lead agency and the county or city has a permit to issue?

A:Procedural issues, including the process and content of the environmental review, could be appealed to thestate agency if itoffers a procedural administrative appeal. Appeals of a local agency's use or non-use of SEPA substantive authority to condition or deny a proposal may be filed with the local agency if they offer an appeal of substantive issues. When administrative appeals are exhausted or unavailable, judicial appeals may be filed.

Q: What is the "action" referred to in part 2 of the notice of action)?

A:It is the underlying government action for the proposal, such asadopting a comprehensive plan, ordinance, or rezone; or issuing a permit or approval. An action is not issuinga SEPA document.

Q: What is a "notice of action taken"?

A:A notice of action is the document used to limit the time a SEPA appeal can be filed when the underlying government action has no set appeal limitations. SEPA rules provide the form while theprocedures for using a notice of action are found the State Environmental Policy Act itself.

Contact information

SEPA Help
sepahelp@ecy.wa.gov
360-407-6922

SEPA FAQ - Washington State Department of Ecology (2024)
Top Articles
Latest Posts
Article information

Author: Margart Wisoky

Last Updated:

Views: 6123

Rating: 4.8 / 5 (78 voted)

Reviews: 93% of readers found this page helpful

Author information

Name: Margart Wisoky

Birthday: 1993-05-13

Address: 2113 Abernathy Knoll, New Tamerafurt, CT 66893-2169

Phone: +25815234346805

Job: Central Developer

Hobby: Machining, Pottery, Rafting, Cosplaying, Jogging, Taekwondo, Scouting

Introduction: My name is Margart Wisoky, I am a gorgeous, shiny, successful, beautiful, adventurous, excited, pleasant person who loves writing and wants to share my knowledge and understanding with you.